How refinement is design? The requirement-centric approach#

Actually, this isn’t something new. If you open any Application Lifecycle Management (ALM) software, you will be surprised to observe that everything is a requirement. From tests to high-level business requirements, it is always free-form specification, plus meta-info. Only the meta-information around the free-form text changes. At the end of the day, what a project needs is a clear understanding of coverage and traceability for each artifact.

I’ve worked as a systems engineer this way without being bothered, because something deeper was happening there. Requirements were not just pass or fail criteria. While this is true at the business level, the more we refine, the more engineering decisions are made, and the more we are actually designing the solution.

An L3 requirement is a technical specification goal; L4 is a specification of what to do to achieve L3. This is because of the entailment relation between a refinement and the refinee.

This is why the req language is requirement-centric. Requirements start as a contractual engagement and transform down to a design constraint. An assumption is also a requirement, but not on the SoI. A req specification is just the accumulation of heterogenous kind, but verifiable properties, loosely named requirements.

A tiny example#

Take a customer who asks for a kettle that boils one liter of water in under three minutes. That is the contractual engagement, it says nothing about how. The kettle delegates the power supply to the mains, as a client would to a contractor.

From a contractual engagement to a design constraint#
package Kitchen
  part Kettle
  part
  part Mains
    let max_power in real \ W \
  part

  requirement Boil_fast top
    on Kettle
    via Mains
  is
    @@
      The [[Kettle]] shall boil one liter of water in less than 3 minutes.
    @@
  requirement

  requirement Power_supply
    on Mains
    derives Boil_fast
  is
    @@
      The [[Mains]] shall supply the power the [[Kettle]] needs to boil one liter of water.
    @@
  requirement

  requirement Supply_limit bottom
    on Mains::max_power
    refines Power_supply
  is
    Mains::max_power >= 2000
  requirement
package

Supply_limit is where the engineering decision lands: heating a liter of water from 20 °C to boiling in 180 s takes about 1.9 kW before losses, so Mains::max_power >= 2000 is a design constraint the customer never asked for. Accumulate enough of these and the specification is the design. Drawn as a chain, each arrow is a decision, and this is how the power ends up allocated to the mains:

        flowchart TD
  subgraph kettle ["Kettle, the client"]
    A["Boil_fast<br/>boil one liter of water<br/>in less than 3 minutes"]
  end
  subgraph mains ["Mains, the supplier"]
    B["Power_supply<br/>supply the power<br/>the kettle needs"]
    C["Supply_limit<br/>max_power ≥ 2000 W"]
  end
  A -->|"delegated to the mains<br/>(via, derives)"| B
  B -->|"sized at about 2 kW<br/>(refines)"| C
    

The chain of decisions that allocates the power to the mains#